Update: Oct. 28, 2025:

Major paving and utility operations have been completed on Dell Range Boulevard. 


Epoxy lane striping is scheduled to begin Wednesday, Oct. 29, and will take place during daytime hours. East and westbound traffic will be reduced to one lane in each direction but will maintain most left hand turns at intersections. The duration for striping is 2 to 3 days and will cause delays. 


On Monday, Nov. 3, installation of thermoplastic crosswalk and turn arrow symbols will begin. This work will affect one intersection at a time and will maintain two eastbound and two westbound lanes of traffic for most of Dell Range. The thermoplastic work duration is 7 to 10 days and will cause minor delays.


Additionally, the contractor will perform some minor grinding operations in various locations throughout the project. This work will begin Monday November 3rd and be performed after 6:00 pm. The grinding operations will take 2 to 3 days. Little to no delays are expected with this work.
All work is dependent on favorable weather and site conditions.